With the great weather the golf course was very busy, and the crew was just as busy working. Since the last update they have gotten close to getting two holes completed. On 16, the greenside bunker drainage was installed, sand was put in, and tomorrow more sod will be put in place along the left side of the green. The fairway bunkers are awaiting drainage and will get sod as soon as the drains are installed.
Number 12 has both bunkers completed and sand installed. The biggest piece of work here was installing additional drainage to capture the water coming off the hillside and green surround. This drain line runs from the back left bunker all the way across the fairway to the creek. Sod will also be installed around the bunkers here tomorrow.
5 had the most dramatic changes. All the old bunkers have been deleted and 2 new greenside bunkers have been rough shaped on the right of the green and 1 bunker in the fairway on the left. Sod has been stripped in the rough up the left side to make room for the fairway expansion.
I've learned that golf construction is a lot like building a house. The dramatic stuff happens quickly, then the details take a while. You get a house under roof then the drywall and plumbing take time to complete. You get sod stripped and bunkers rough shaped, then you add drainage, sand, and sod.
.JPG) |
Not the best pic, but you can see some of the changes. |